Not included

TAXES AND EXPENSES NOT INCLUDED
- VAT on the house (10%)
- Property Transfer Tax (ITP) on the land (10%) or, in some cases, VAT on the land (21%)
- Notary fees for the purchase of the land
- Building permit: between 3.5% and 4% of the price of the house (excluding the land)
*Some municipalities may require a security deposit - Municipal fees, technical certificates, street closure permits, waste management, containers, and soil disposal to landfill
- Costs associated with post-construction formalities after obtaining the Final Works Certificate, including legalization and registration of the property:
- Certificate of occupancy
- First occupancy license
- Building description certificate
- Declaration of new construction
- Stamp duty
- Building logbook
- Energy performance certificate (design and final stages)
- Cadastral registration, etc.
WORKS AND ITEMS NOT INCLUDED
- Swimming pool
- Garage
- Possible construction fencing (as required by some municipalities)
- Outdoor paving
- Terraces, pergolas, and other exterior elements
- Appliances
- Landscaping / garden
- Large windows (larger than 140 × 210 cm)
- Water tanks
- Main utility meters (electricity, water, sewage)
- Utility consumption during construction
- Perimeter fencing
- Tree felling
- Earthworks: The price includes work planned for flat terrain, always on firm ground and without any complications.
- The type of final foundation, various movements, and excavation for the pool are always determined during the earthworks phase under the supervision of the Architect.
- Any modifications to the price will be assessed separately. (Rocks, Clay, Slopes, Ramps, etc.)
We have a network of collaborating companies for whatever the buyer requires